The short version. Three different numbers, and people mix them up constantly.

The three numbers

Submittal number

Identifies the item — usually tied to the spec section. It doesn’t change.

Version

Which iteration of that item you sent.

Revision

The resubmission count after a rejection or a “revise and resubmit.”

Create it

1

Pick the spec section

From your published spec book. If the list is empty, the book isn’t published. → Uploaded vs. Published
2

Accept or override the suggested number

DirtView suggests the next number. Override it if your GC or the owner requires their own numbering — but then be consistent for the whole job.
3

Attach the package

Product data, shop drawings, samples documentation — whatever the section requires.
4

Set the review routing

5

Submit

A draft submittal is not submitted, and the clock hasn’t started.

Which iteration the list shows

The submittal log shows one row per item — the current iteration, not every version you ever sent. To see the earlier ones, open the submittal and look at its versions.

Next

Submittal review

In Review, Outstanding, Approved, Rejected.